== Title ==
 
== Title ==
  
 +
'''Extending the Metal Space'''
  
 
== Proposer ==
 
== Proposer ==
 +
Alan, Toby, James and Barny
  
 +
== Date proposed ==
 +
10 October 2020
 +
 +
== Date for Decision ==
 +
17 October 2020
 +
 +
 +
== What is being asked for ==
 +
 +
A budget for infrastructure improvements and some help preparing, painting the workshop and moving things around
  
== Date proposed ==
+
Some storage and racking for tools and stock
  
 +
A basic set of tooling so members do not need to borrow either Lion House or Toby's tools
  
== Date for Decision ==
+
[[File:Metalspace1.jpg|460px|Metal Space]]
Usually one week after posting
+
[[File:Metalspace plan.jpg|600px|Floor plan]]
  
 
== Cost ==
 
== Cost ==
 +
Budget of £800 to £1,000
 +
* Painting the floor  - £100
 +
* Racking and Storage - £200
 +
* Workbench          - ?
 +
* Extra tooling      - £400
 +
* PPE and first aid  - £150
 +
 +
== Why/how this will be good to have ==
 +
To expand into and make the Metal space a nicer, safer envirioment with a cleaner looking and well laid out workshop. This will make the place more inviting and better working place for all our members.
  
 +
A group of us met in the space to discuss what needed to be done. A floorplan was surveyed and drawing created (see above). The final layout of equipment is work in progress
  
== What is being asked for ==
+
* To delinearate the workshop from existing tenants a division a partition would be needed, this will be made up from storage racking and workbenchs and dividers. We have some storage but will need some more. 
 +
 
 +
* The floor will be painted (probably slate grey) starting with the bay furtherest from the door.
 +
 
 +
* The walls will be cleared of superfluous wiring and other bits and then painted
 +
 
 +
* Tool storage on the walls
  
== Why/how this will be good to have ==
+
The plan is to arrange the workshop into areas:
  
 +
    Machining area:    Harrision Lathe, milling machine, Elliot drill bench
 +
    Fabrication area:  Air compressor and tools, cut off saw, grinder, assembly bench
 +
    Welding area:      Mig, Tig and arc welders, welding bench
 +
    Hot metals area:  Forge, anvil, casting equipment
 +
    CNC machine area:  Space should be allowed for the CNC plasma cutter when it is functional
  
 
== Who is for it ==
 
== Who is for it ==
 +
Alan<br>
 +
Toby<br>
 +
James<br>
 +
Barny<br>
 +
Brian<br>
 +
Peter<br>
 +
Percy<br>
 +
Tim<br>
 +
 +
 +
 +
 +
== Comments ==<br>
  
 +
See Slack #decision-making and #metal-space <br>
  
== Who is against it and why ==
+
https://wiki.norwichhackspace.org/index.php?title=Metal_workshop_improvements_mk1#Any_tools_we_need
  
 
== Outcome ==
 
== Outcome ==
Agreed - Completed
+
Approved - 17 October 2020 Ben summerised.
Agreed - waiting action
 
Rejected -
 
More information required
 
On hold
 
  
 
== Actions ==
 
== Actions ==
Who is taking this forward and what will they do?
+
Who is taking this forward and what will they do? - Toby and Alan will act as project leaders
 +
 
 +
There is a quite a lot of work to achieve the final outcome.
 +
A few working parties should get quite a lot done.
 +
 
 +
<s>Buy paint etc and material for partition</s><br>
 +
 
 +
<s>Start to clear, prepare and paint the floor furthest from the door</s><br>
 +
 
 +
Partition off from rest of tenants with existing shelving/cupboards<br>
 +
 
 +
As work progresses move towards the door
 +
 
 +
Move exisitng machinery and benches into position
 +
 
 +
Buy tooling as needed
 +
 
 +
Organise first aid and Covid section
 +
 
 +
Write-up workshop induction
 +
 
 +
Write-up instructions lathe, milling machine, and other tools

Latest revision as of 01:49, 25 October 2020

Title

Extending the Metal Space

Proposer

Alan, Toby, James and Barny

Date proposed

10 October 2020

Date for Decision

17 October 2020


What is being asked for

A budget for infrastructure improvements and some help preparing, painting the workshop and moving things around

Some storage and racking for tools and stock

A basic set of tooling so members do not need to borrow either Lion House or Toby's tools

Metal Space Floor plan

Cost

Budget of £800 to £1,000

  • Painting the floor - £100
  • Racking and Storage - £200
  • Workbench - ?
  • Extra tooling - £400
  • PPE and first aid - £150

Why/how this will be good to have

To expand into and make the Metal space a nicer, safer envirioment with a cleaner looking and well laid out workshop. This will make the place more inviting and better working place for all our members.

A group of us met in the space to discuss what needed to be done. A floorplan was surveyed and drawing created (see above). The final layout of equipment is work in progress

  • To delinearate the workshop from existing tenants a division a partition would be needed, this will be made up from storage racking and workbenchs and dividers. We have some storage but will need some more.
  • The floor will be painted (probably slate grey) starting with the bay furtherest from the door.
  • The walls will be cleared of superfluous wiring and other bits and then painted
  • Tool storage on the walls

The plan is to arrange the workshop into areas:

   Machining area:    Harrision Lathe, milling machine, Elliot drill bench 
   Fabrication area:  Air compressor and tools, cut off saw, grinder, assembly bench 
   Welding area:      Mig, Tig and arc welders, welding bench
   Hot metals area:   Forge, anvil, casting equipment
   CNC machine area:  Space should be allowed for the CNC plasma cutter when it is functional

Who is for it

Alan
Toby
James
Barny
Brian
Peter
Percy
Tim



== Comments ==

See Slack #decision-making and #metal-space

https://wiki.norwichhackspace.org/index.php?title=Metal_workshop_improvements_mk1#Any_tools_we_need

Outcome

Approved - 17 October 2020 Ben summerised.

Actions

Who is taking this forward and what will they do? - Toby and Alan will act as project leaders

There is a quite a lot of work to achieve the final outcome. A few working parties should get quite a lot done.

Buy paint etc and material for partition

Start to clear, prepare and paint the floor furthest from the door

Partition off from rest of tenants with existing shelving/cupboards

As work progresses move towards the door

Move exisitng machinery and benches into position

Buy tooling as needed

Organise first aid and Covid section

Write-up workshop induction

Write-up instructions lathe, milling machine, and other tools