Difference between revisions of "04/20"
Alanscrase (talk | contribs) (04/20) |
Alanscrase (talk | contribs) |
||
| (34 intermediate revisions by 2 users not shown) | |||
| Line 1: | Line 1: | ||
== Title == | == Title == | ||
| + | '''Extending the Metal Space''' | ||
== Proposer == | == Proposer == | ||
| + | Alan, Toby, James and Barny | ||
| + | == Date proposed == | ||
| + | 10 October 2020 | ||
| + | |||
| + | == Date for Decision == | ||
| + | 17 October 2020 | ||
| + | |||
| + | |||
| + | == What is being asked for == | ||
| + | |||
| + | A budget for infrastructure improvements and some help preparing, painting the workshop and moving things around | ||
| − | + | Some storage and racking for tools and stock | |
| + | A basic set of tooling so members do not need to borrow either Lion House or Toby's tools | ||
| − | + | [[File:Metalspace1.jpg|460px|Metal Space]] | |
| − | + | [[File:Metalspace plan.jpg|600px|Floor plan]] | |
== Cost == | == Cost == | ||
| + | Budget of £800 to £1,000 | ||
| + | * Painting the floor - £100 | ||
| + | * Racking and Storage - £200 | ||
| + | * Workbench - ? | ||
| + | * Extra tooling - £400 | ||
| + | * PPE and first aid - £150 | ||
| + | |||
| + | == Why/how this will be good to have == | ||
| + | To expand into and make the Metal space a nicer, safer envirioment with a cleaner looking and well laid out workshop. This will make the place more inviting and better working place for all our members. | ||
| + | |||
| + | A group of us met in the space to discuss what needed to be done. A floorplan was surveyed and drawing created (see above). The final layout of equipment is work in progress | ||
| + | |||
| + | * To delinearate the workshop from existing tenants a division a partition would be needed, this will be made up from storage racking and workbenchs and dividers. We have some storage but will need some more. | ||
| + | |||
| + | * The floor will be painted (probably slate grey) starting with the bay furtherest from the door. | ||
| + | * The walls will be cleared of superfluous wiring and other bits and then painted | ||
| − | + | * Tool storage on the walls | |
| − | + | The plan is to arrange the workshop into areas: | |
| + | Machining area: Harrision Lathe, milling machine, Elliot drill bench | ||
| + | Fabrication area: Air compressor and tools, cut off saw, grinder, assembly bench | ||
| + | Welding area: Mig, Tig and arc welders, welding bench | ||
| + | Hot metals area: Forge, anvil, casting equipment | ||
| + | CNC machine area: Space should be allowed for the CNC plasma cutter when it is functional | ||
== Who is for it == | == Who is for it == | ||
| + | Alan<br> | ||
| + | Toby<br> | ||
| + | James<br> | ||
| + | Barny<br> | ||
| + | Brian<br> | ||
| + | Peter<br> | ||
| + | Percy<br> | ||
| + | Tim<br> | ||
| − | == | + | |
| + | |||
| + | == Comments ==<br> | ||
| + | |||
| + | See Slack #decision-making and #metal-space <br> | ||
| + | |||
| + | https://wiki.norwichhackspace.org/index.php?title=Metal_workshop_improvements_mk1#Any_tools_we_need | ||
== Outcome == | == Outcome == | ||
| − | + | Approved - 17 October 2020 Ben summerised. | |
| − | + | ||
| − | + | == Actions == | |
| − | + | Who is taking this forward and what will they do? - Toby and Alan will act as project leaders | |
| − | + | ||
| + | There is a quite a lot of work to achieve the final outcome. | ||
| + | A few working parties should get quite a lot done. | ||
| + | |||
| + | <s>Buy paint etc and material for partition</s><br> | ||
| + | |||
| + | <s>Start to clear, prepare and paint the floor furthest from the door</s><br> | ||
| + | |||
| + | Partition off from rest of tenants with existing shelving/cupboards<br> | ||
| + | |||
| + | As work progresses move towards the door | ||
| + | |||
| + | Move exisitng machinery and benches into position | ||
| + | |||
| + | Buy tooling as needed | ||
| + | |||
| + | Organise first aid and Covid section | ||
| + | |||
| + | Write-up workshop induction | ||
| + | |||
| + | Write-up instructions lathe, milling machine, and other tools | ||
Latest revision as of 00:49, 25 October 2020
Contents
Title
Extending the Metal Space
Proposer
Alan, Toby, James and Barny
Date proposed
10 October 2020
Date for Decision
17 October 2020
What is being asked for
A budget for infrastructure improvements and some help preparing, painting the workshop and moving things around
Some storage and racking for tools and stock
A basic set of tooling so members do not need to borrow either Lion House or Toby's tools
Cost
Budget of £800 to £1,000
- Painting the floor - £100
- Racking and Storage - £200
- Workbench - ?
- Extra tooling - £400
- PPE and first aid - £150
Why/how this will be good to have
To expand into and make the Metal space a nicer, safer envirioment with a cleaner looking and well laid out workshop. This will make the place more inviting and better working place for all our members.
A group of us met in the space to discuss what needed to be done. A floorplan was surveyed and drawing created (see above). The final layout of equipment is work in progress
- To delinearate the workshop from existing tenants a division a partition would be needed, this will be made up from storage racking and workbenchs and dividers. We have some storage but will need some more.
- The floor will be painted (probably slate grey) starting with the bay furtherest from the door.
- The walls will be cleared of superfluous wiring and other bits and then painted
- Tool storage on the walls
The plan is to arrange the workshop into areas:
Machining area: Harrision Lathe, milling machine, Elliot drill bench Fabrication area: Air compressor and tools, cut off saw, grinder, assembly bench Welding area: Mig, Tig and arc welders, welding bench Hot metals area: Forge, anvil, casting equipment CNC machine area: Space should be allowed for the CNC plasma cutter when it is functional
Who is for it
Alan
Toby
James
Barny
Brian
Peter
Percy
Tim
== Comments ==
See Slack #decision-making and #metal-space
https://wiki.norwichhackspace.org/index.php?title=Metal_workshop_improvements_mk1#Any_tools_we_need
Outcome
Approved - 17 October 2020 Ben summerised.
Actions
Who is taking this forward and what will they do? - Toby and Alan will act as project leaders
There is a quite a lot of work to achieve the final outcome. A few working parties should get quite a lot done.
Buy paint etc and material for partition
Start to clear, prepare and paint the floor furthest from the door
Partition off from rest of tenants with existing shelving/cupboards
As work progresses move towards the door
Move exisitng machinery and benches into position
Buy tooling as needed
Organise first aid and Covid section
Write-up workshop induction
Write-up instructions lathe, milling machine, and other tools