Difference between revisions of "04/20"
Alanscrase (talk | contribs) |
Alanscrase (talk | contribs) |
||
Line 13: | Line 13: | ||
== Cost == | == Cost == | ||
− | + | Budget of £800 to £1,000 | |
− | |||
− | |||
* Painting the floor - £100 | * Painting the floor - £100 | ||
* Racking and Storage - £200 | * Racking and Storage - £200 | ||
* Workbench - ? | * Workbench - ? | ||
− | * Extra tooling - | + | * Extra tooling - £400 |
− | * PPE | + | * PPE and first aid - £150 |
+ | == What is being asked for == | ||
+ | A budget for infrastructure and some help preparing, painting the workshop and moving things around | ||
+ | Some storage and racking for tools and stock | ||
+ | A basic set of tooling so do not need to borrow either Lion HOuse or Toby's tools | ||
+ | |||
== Why/how this will be good to have == | == Why/how this will be good to have == | ||
To expand into and make the Metal space a nicer and safer envirioment a cleaner looking and well laid out workshop. This will make the place a better working place for all. | To expand into and make the Metal space a nicer and safer envirioment a cleaner looking and well laid out workshop. This will make the place a better working place for all. | ||
Line 44: | Line 47: | ||
== Who is for it == | == Who is for it == | ||
+ | Alan | ||
+ | Toby | ||
+ | James | ||
+ | Barney | ||
Line 49: | Line 56: | ||
== Outcome == | == Outcome == | ||
− | + | Awaiting decision | |
− | |||
− | |||
− | |||
− | |||
== Actions == | == Actions == | ||
Line 61: | Line 64: | ||
A few working parties should get quite a lot done. | A few working parties should get quite a lot done. | ||
+ | Buy paint etc and material for partition | ||
Start to clear, prepare and paint the floor furthest from the door | Start to clear, prepare and paint the floor furthest from the door | ||
Partition off from rest of tenants with existing shelving/cupboards | Partition off from rest of tenants with existing shelving/cupboards | ||
− | As work progresses move towards the door | + | As work progresses move towards the door. |
+ | Move exisitng machinery and benches into position | ||
+ | Buy tooling as needed | ||
+ | Organise first aid and Covid section | ||
+ | Write-up workshop induction | ||
+ | Write-up instructions lathe, milling machine, and other tools |
Revision as of 11:06, 5 October 2020
Contents
Title
Extending the Metal Space
Proposer
Alan, Toby, James and Barny
Date proposed
5 October 2020
Date for Decision
12 October 2020
Cost
Budget of £800 to £1,000
- Painting the floor - £100
- Racking and Storage - £200
- Workbench - ?
- Extra tooling - £400
- PPE and first aid - £150
What is being asked for
A budget for infrastructure and some help preparing, painting the workshop and moving things around Some storage and racking for tools and stock A basic set of tooling so do not need to borrow either Lion HOuse or Toby's tools
Why/how this will be good to have
To expand into and make the Metal space a nicer and safer envirioment a cleaner looking and well laid out workshop. This will make the place a better working place for all.
A group of us met in the space to discuss what needed to be done. A floorplan was surveyed and drawing created. The final layout of equipment is work in progress
- To delinearate the workshop from existing tenants a division a partition would be needed, this will be made up from storage racking and workbenchs and dividers. We have some storage but will need some more.
- The floor will be painted (probably slate grey) starting with the bay furtherest from the door.
- The walls will be cleared of superfulious wiring and other bits and then painted
- Tool storage on the walls
The plan is arrange the workshop into areas:
Machining area: Harrision Lathe, milling machine, Elliot drill bench Fabrication area: Air comprerssor and tools, cut off saw, grinder, assembly bench Welding area: Mig, Tig and arc welders, welding bench Hot metals area: Forge, anvil, casting equipment CNC machine area: Space should be allowed for the CNC plasma cutter when it is functional
Who is for it
Alan Toby James Barney
Who is against it and why
Outcome
Awaiting decision
Actions
Who is taking this forward and what will they do?
There is a quite a lot of work to achieve the final outcome. A few working parties should get quite a lot done.
Buy paint etc and material for partition Start to clear, prepare and paint the floor furthest from the door Partition off from rest of tenants with existing shelving/cupboards As work progresses move towards the door. Move exisitng machinery and benches into position Buy tooling as needed Organise first aid and Covid section Write-up workshop induction Write-up instructions lathe, milling machine, and other tools